----- chatbot ID----
+91 - 94899 24055 project@vayuduth.com

Our Work in HOEC

Major EPC contractor is M/S Technip KT 

Value of the project Rs.15.00 CR

Our Team involved in this project

  • Project Manager – 01
  • Site Engineering -09
  • Documentation work – 2
  • Site Safety Engineer – 03
  • Total employees uitlizated the project – 112
  • Total hours – 2208 hrs

Total Hours

Budjet in Cr.

%

client satisfaction

The project’s major EPC contractor is M/S Technip KT Indin Limited, Delhi. We are the subcontractor to them

MEP Contractor Value of the project Rs.15.00 CR

  • Pipeline fabrication with erection, commissioning including an extra joint test with insulation painting
  • Pre Engineered Building Including civil /electrical / inside of the equipment installation Insulation supply with application / Fire fitting system /commissioning
  • Reporting to Mr Millappan Site Incharge Techniip KT India Limited
  • Performance Reporting to MR. Jalapathy RCM Technip KT India Limited

Duration 92 days (24 /7)

Technicians Electrical – 10

Instrumentation Engineer -5

Insulation Technicians -25

Fabrication Erection – 45

Crane 12 MT – 2 Nos

Case Study - Our Work in DSSL

We are the Director Contract form plan equipment supply testing and commissioning MEP Service. 

Project Value: Rs.116.00 Cr

Case Study - Our work in IOTL

We are doing the business with IOTL / Namkkal Puduchtharam location Tamilnadu

Duration: 30 days 24 X 7

Ready to Start?

Get in Touch